FERC chair slams PJM ‘mess’ as country’s largest grid operator delays power auction
PJM Interconnection submitted an amended filing proposing a March 2027 auction, complete with new cost-allocation and collateral rules, following regulatory setbacks. The grid operator previously missed its capacity target by 6,831 MW in its 2028/29 auction. Federal regulators rejected PJM's bring-your-own-capacity rule on Oct. 9, which would have forced large electricity users and data centers to cut power during grid emergencies. Regulators instead left curtailment oversight to individual states. A Department of Energy emergency order subsequently unlocked 35GW of backup generation three days after the federal rejection.
Listen to Live Briefing
Real-time synthesized voice briefing · Live Feeds Desk
- ✓ FERC threw out PJM's bring-your-own-capacity rule on October 9.
- ✓ A DOE emergency order unlocked 35GW of backup generation three days after the FERC decision.
- ✓ PJM's 2028/29 auction missed its capacity target by 6,831 MW.
- ✓ PJM submitted an amended filing on October 29 proposing a March 2027 auction with new cost-allocation and collateral rules.
What changed
PJM filed an amended backstop procurement plan on Oct. 29 targeting a March 2027 auction restart with updated cost-allocation and collateral rules.
Live updates
-
PJM Proposes March 2027 Auction After FERC Rejects Data Center Plan
PJM Interconnection submitted an amended filing proposing a March 2027 auction, complete with new cost-allocation and collateral rules, following regulatory setbacks. The grid operator previously missed its capacity target by 6,831 MW in its 2028/29 auction. Federal regulators rejected PJM's bring-your-own-capacity rule on Oct. 9, which would have forced large electricity users and data centers to cut power during grid emergencies. Regulators instead left curtailment oversight to individual states. A Department of Energy emergency order subsequently unlocked 35GW of backup generation three days after the federal rejection.
Why it matters
Rapidly growing artificial intelligence demand threatens to overwhelm power supplies across the grid operator region, forcing a scramble for reliable energy sources. Federal regulators previously rejected PJM proposals while allowing a registry to track major electricity users. State lawmakers are now grappling with the fallout, shifting policy fights to local jurisdictions such as Annapolis and Illinois.
What is confirmed
- FERC threw out PJM's bring-your-own-capacity rule on October 9.
- A DOE emergency order unlocked 35GW of backup generation three days after the FERC decision.
- PJM's 2028/29 auction missed its capacity target by 6,831 MW.
- PJM submitted an amended filing on October 29 proposing a March 2027 auction with new cost-allocation and collateral rules.
Still unconfirmed
- FirstEnergy's Monongahela Power contends that PJM's advanced scheduling of gas-fired power plants during Winter Storm Fern may have violated grid rules.
What to watch next
- Federal regulatory response to PJM's October 29 amended filing and proposed March 2027 auction.
- State-level legislative actions in Illinois and Maryland regarding data center energy rules and curtailment.
confidence 100%Sources used for this update (9)
- americascoal.substack.com — THE DIGITAL LOAD: FERC Rejects PJM’s Curtail-First Large-Load ...
- lmunck.com — FERC rejected the rule that made data centres bring their own ...
- thecapitalatlas.substack.com — PJM can list data centers before it can curtail them
- ltdsolarconsulting.com — FERC Rejected PJM's Data Center Fix. Can Illinois's POWER Act ...
- www.themarylandwire.com — Data Center Grid Fight Goes to Annapolis - themarylandwire.com
- finance.yahoo.com — PJM urges FERC to dismiss Mon Power ‘fishing expedition ...
- centralintelligence.co — FERC Tightens Data Center Grid Rules | Data Centers | Central ...
- marcellusdrilling.com — PJM Fixes Data Center Power Auction, Aims for March 2027 ...
- microgridmedia.com — PJM backstop procurement: March 2027 bidding proposed
-
FERC Rejects PJM Plan to Cut Data Center Power
Federal energy regulators rejected a proposal from PJM Interconnection that would have forced large data centers and other major electricity users to cut power during grid emergencies. The Federal Energy Regulatory Commission issued the decision on Oct. 9, leaving curtailment rules largely in the hands of individual states. The rejected proposal aimed to manage surging artificial intelligence-driven demand that threatens to outpace available supply across the grid operator's 13-state and District of Columbia region. However, regulators did approve a separate measure allowing PJM to establish a large load registry to track major electricity users.
Why it matters
The ruling comes as the nation's largest power grid operator attempts to navigate projected generation gaps and soaring electricity demand. PJM had asked federal regulators for approval to shut off data centers first when the grid sits on the verge of a blackout. The rejection complicates efforts by grid managers to handle heavy consumption spikes from large facilities that fail to secure additional power generation.
What is confirmed
- The Federal Energy Regulatory Commission rejected portions of PJM Interconnection's proposal on Oct. 9 that would have required certain large electricity customers to reduce consumption during emergencies.
- Regulators approved a measure allowing PJM to implement a large load registry to track major electricity users.
- PJM serves Maryland and twelve other states plus the District of Columbia.
What to watch next
- Whether PJM provides additional justification for a renewed early-curtailment plan
- State-level implementation of electricity curtailment rules for data centers
confidence 100%Sources used for this update (9)
- www.utilitydive.com — Solving California’s energy affordability crisis can help the whole nation | Utility Dive
- www.newsweek.com — Electric Company Under Blackout Emergency Order Can't ...
- www.yahoo.com — Federal energy regulators shoot down grid operator’s plan to ...
- www.euci.com — PJM chided by federal energy officials over its emergency ...
- www.latitudemedia.com — FERC rejected PJM’s data center curtailment plan. What’s next ...
- dailycaller.com — Federal Regulators Reject Largest US Grid Operator’s Plan To ...
- www.wypr.org — Federal regulators reject major data center guardrails from regional grid operator for Maryland | WYPR
- dailycallernewsfoundation.org — Federal Regulators Reject Largest US Grid Operator’s Plan To ...
- vector.news — Regulator rejects PJM plan to curtail data centers first
-
FERC chair criticizes PJM's 'mess' as grid operator delays power auction
The PJM Interconnection's emergency reliability backstop auction has been delayed by five months, amid concerns over capacity shortages and soaring electricity demand across its 13-state and District of Columbia region. The Federal Energy Regulatory Commission (FERC) partially approved PJM's plan, but expressed concerns over cost allocation and collateral rules. The Department of Energy urged regulators to track generation projects' progress to protect residential ratepayers.
Why it matters
The PJM Interconnection is the country's largest grid operator, serving over 65 million people. Its delayed auction has left the region uncertain about future pricing and capacity shortages. The FERC's partial approval and concerns reflect ongoing debates over how to manage large load growth, particularly from data centers.
What is confirmed
- The PJM Interconnection's plan for curtailing large loads that don't have matching new generation intrudes on state jurisdiction and appears to be discriminatory, according to the Federal Energy Regulatory Commission.
- PJM expects Engie's two storage projects totaling nearly 1.7 GW and LS Power's 455-MW gas-fired uprate to be online by mid-2029.
- The Department of Energy filed a comment with FERC on October 7 backing an order for PJM to rewrite its cost allocation plan for a 6.8 GW capacity buy.
- PJM must refile its proposal by October 29.
Still unconfirmed
- The FERC chair described PJM's situation as a 'mess'
What to watch next
- PJM's refiled proposal by October 29
- FERC's next order on PJM's revised plan
- The impact of delayed auctions on electricity prices and capacity shortages in PJM's region
confidence 85%Sources used for this update (4)
- www.utilitydive.com — Generation - Utility Dive
- mgrid.org — DOE Makes Its First FERC Filing in Five Years on PJM’s 6.8 GW ...
- www.publicpower.org — FERC Accepts Elements of PJM Proposal Tied to Large Loads ...
- www.yahoo.com — FERC rejects most of PJM’s large load interconnection plan
-
FERC Delays PJM Power Auction
Federal regulators have pushed back PJM Interconnection's emergency reliability backstop auction by five months following partial approval of the data center-focused plan. The delay leaves capacity shortages, soaring electricity demand, and future pricing uncertain across the 13-state and District of Columbia region. The Department of Energy urged regulators to protect residential ratepayers from large load costs by tracking whether specific generation projects actually enter service, are delayed, or are cancelled. Federal energy officials criticized the original proposal over serious flaws in cost allocation and collateral rules.
Why it matters
PJM serves as the country's largest grid operator, managing electricity supplies across a vast mid-Atlantic territory facing severe demand spikes from data centers. The federal intervention highlights growing friction between grid operators and regulators over who should pay for new generation capacity. Without clear tracking mechanisms, household consumers risk bearing the heavy financial burdens of infrastructure built to serve massive commercial technology loads.
What is confirmed
- FERC conditionally approved and suspended PJM's Reliability Backstop Procurement due to flaws in cost allocation.
- PJM delayed its planned reliability backstop procurement auction for data centers as of September 29, 2026.
- The Department of Energy stated that tracking whether projects enter service, are delayed, or are cancelled can help assign new generation costs to responsible customers.
What to watch next
- PJM's release of revised auction rules addressing cost allocation and collateral concerns.
- Further filings from the Department of Energy regarding ratepayer protections for large load costs.
confidence 100%Sources used for this update (7)
- energyedge.com — FERC Delays PJM Reliability Backstop Auction as Capacity ...
- www.utilitydive.com — DOE presses PJM on ratepayer protections from large load costs | Utility Dive
- thefactum.ai — FERC Suspends PJM's Reliability Backstop Procurement Amid ...
- www.yahoo.com — DOE presses PJM on ratepayer protections from large load costs
- www.zerohedge.com — "Deeply Flawed": Biggest US Grid Scraps Emergency ... - Zerohedge
- www.jepic-usa.org — JEPIC-USA
- www.utilitydive.com — Top electric power sector and utility conferences in 2027 | Utility Dive
-
FERC Halts PJM Data Center Power Auction
Federal regulators have halted a specialized power auction planned by PJM Interconnection hours before it was scheduled to open. The grid operator intended to secure thousands of megawatts of new electricity to cover surging demand driven by data centers across its territory covering 13 states and the District of Columbia. Federal energy officials criticized the proposal as deeply flawed, citing serious concerns regarding rules for cost allocation and collateral that could impose major financial burdens on residential households while market participants handle the sudden delay.
Why it matters
PJM Interconnection manages the high-voltage electric transmission system for a broad mid-Atlantic and Midwestern region including Pennsylvania, Ohio, and West Virginia. The grid operator attempted to run a special emergency auction to fill a multi-gigawatt capacity shortfall. Regulatory intervention exposes deep friction between federal oversight and regional market rules as artificial intelligence data centers strain local power grids.
What is confirmed
- PJM Interconnection planned to open a one-time emergency auction to buy 6,831 megawatts of brand-new power.
- The auction was scheduled to open on September 30 before federal regulators froze the plan.
- PJM operates the electric grid in all or part of 13 states and the District of Columbia.
Still unconfirmed
- A PJM committee shut out states during the controversy surrounding the emergency auction.
What to watch next
- Revised cost allocation and collateral rules submitted by PJM to federal regulators
- New dates announced for the delayed data center power auction
confidence 95%Sources used for this update (4)
- thequadreport.com — FERC slams PJM emergency auction; PJM committee shuts out ...
- www.utilitydive.com — Grid Security & Reliability News | Utility Dive
- marcellusdrilling.com — FERC Slams Brakes on PJM's 'Deeply Flawed' Data Center Power ...
- capwolf.com — PJM Delays Data Center Power Auction After FERC Review
-
FERC Slams PJM Grid Mess After Delaying Power Auction
Federal regulators have conditionally approved a reliability backstop plan from PJM Interconnection while delaying its implementation and criticizing the grid operator over capacity rules and cost allocations. PJM postponed its data center power auction after federal regulators raised serious concerns regarding flawed cost allocation and collateral rules carrying billion-dollar consumer implications. This regulatory friction creates acute market uncertainty for power stocks as the region attempts to manage surging electricity demand driven by artificial intelligence.
Why it matters
The standoff highlights mounting tensions between regional grid operators and federal regulators over how to finance and manage rapid infrastructure growth. PJM currently manages between 12 and 17 gigawatts of data center load, forcing operators to seek backstop power supplies after missing reserve margin targets. Disagreements over who bears these massive financial burdens threaten to destabilize energy markets across the country's largest grid.
What is confirmed
- PJM delayed its backstop capacity auction after federal regulators raised concerns about cost allocation and other key plan elements.
- The Federal Energy Regulatory Commission conditionally approved a reliability backstop plan from PJM Interconnection while delaying its implementation.
- PJM has 12 to 17 gigawatts of data center load.
Still unconfirmed
- Disputes over collateral rules and cost allocation carry billion-dollar consumer implications.
What to watch next
- Resolution of the cost allocation and collateral rule disputes by federal regulators.
- Rescheduling of the delayed reliability backstop capacity auction by PJM.
confidence 90%Sources used for this update (5)
- www.utilitydive.com — Energy regulation & Policy News | Utility Dive
- tetmo.com — FERC Slams PJM Grid Mess Following Power Auction Delay and ...
- solmarcapital.co — PJM delays reliability auction as FERC rejects key plan ...
- www.thelogicalinsight.com — PJM Delays Data Center Power Auction After Federal Regulators ...
- www.bocvip.com — FERC chair slams PJM ‘mess’ as country’s largest grid ...
-
FERC Delays PJM Power Auction Amid Cost Concerns
The Federal Energy Regulatory Commission has conditionally approved a reliability backstop plan from PJM Interconnection while delaying its implementation and criticizing the grid operator's handling of capacity rules. PJM had scheduled an auction to accept offers for backstop power supplies after failing to meet its reserve margin targets. However, federal regulators intervened due to serious concerns over how data center costs would be allocated. The delay creates acute market uncertainty for power stocks as the region struggles to manage surging electricity demand from artificial intelligence.
Why it matters
PJM serves as the country's largest grid operator, managing power supplies across multiple states. The operator faced a significant capacity shortfall, creating a gap that required urgent backstop procurement. At the same time, the rapid proliferation of energy-intensive data centers has strained regional capacity and raised alarms about consumer protection.
What is confirmed
- PJM Interconnection planned to accept offers for backstop power supplies from Sept. 30 through Oct. 21.
- The Federal Energy Regulatory Commission partially approved the grid operator's plan with a focus on cost allocation concerns.
Still unconfirmed
- TD Cowen warned of acute market uncertainty for utility stocks including CEG, NRG, and TLN following the regulatory delay.
What to watch next
- Revised cost allocation proposals submitted by PJM to the Federal Energy Regulatory Commission.
- New dates announced for the delayed backstop power auction.
confidence 100%Sources used for this update (10)
- utilitydive.com — FERC chair slams PJM ‘mess’ as country’s largest grid operator delays power auction
- Bloomberg.com — Biggest US Grid Suspends Plan for Data Center Power Auction
- Yahoo Finance — CEG, NRG, TLN Stocks In Spotlight: TD Cowen Warns Of ‘Acute’ Uncertainty After FERC Delays PJM’s Plan To Meet AI Demand
- Energy-Storage.News — PJM capacity reforms require urgent state action to protect ratepayers, says NRDC
- TradingView — FERC asks grid operator PJM to revise plan to shield homes from data center costs
- RTO Insider — FERC Conditionally Approves PJM Backstop Procurement, Delays Implementation
- Daily Energy Insider — Rep. Pallone makes recommendations to FERC to improve PJM’s data center proposals
- energynews.pro — FERC Approves PJM's Reliability Backstop Plan for 6,831 MW Gap
- www.utilitydive.com — FERC chair slams PJM ‘mess’ as country’s largest grid operator delays power auction | Utility Dive
- www.utilitydive.com — Data center backup power contributes to health risks: report | Utility Dive
Community Sentiment: How do you assess this situation?
Voice your perspective · Real-time aggregated sentiment from the Live Feeds community