LAX’s nightmare ‘people mover’ delayed again three years after scheduled opening
The LAX people mover project, initially set to open in 2023, is now expected to open in January 2027, with a current estimated cost of $3.3 billion, over $1 billion above its original budget. The 2.25-mile automated system, designed to connect LAX terminals to parking facilities, rental car hubs, and the Metro public transit system, has faced multiple delays due to technical issues, including damaged guide beams, malfunctioning expansion joints, and power rail damage.
Listen to Live Briefing
Real-time synthesized voice briefing · Live Feeds Desk
- ✓ The LAX people mover project is currently about 99% complete.
- ✓ The project has a current estimated cost of $3.3 billion, up from $1.9 billion.
- ✓ The people mover system is expected to open in January 2027.
- ✓ The project is 3 years behind its initial schedule.
What changed
The latest delay follows reports of electrical blasts and fire damage to the power rail, further pushing back the opening date.
Live updates
-
LAX $3.3B 'people mover' rail project delayed again
The LAX people mover project, initially set to open in 2023, is now expected to open in January 2027, with a current estimated cost of $3.3 billion, over $1 billion above its original budget. The 2.25-mile automated system, designed to connect LAX terminals to parking facilities, rental car hubs, and the Metro public transit system, has faced multiple delays due to technical issues, including damaged guide beams, malfunctioning expansion joints, and power rail damage.
Why it matters
The project has become a contentious issue in the mayoral race and has been subject to legal disputes, including a lawsuit by the Texas-based contractor against LA World Airports. The delays and cost overruns have raised concerns about taxpayer-funded infrastructure projects in Southern California.
What is confirmed
- The LAX people mover project is currently about 99% complete.
- The project has a current estimated cost of $3.3 billion, up from $1.9 billion.
- The people mover system is expected to open in January 2027.
- The project is 3 years behind its initial schedule.
Still unconfirmed
- A grand jury probe is investigating the project's delays and cost overruns.
What to watch next
- The project's opening date in January 2027
- The outcome of the lawsuit between the contractor and LA World Airports
- Further updates on the project's technical issues and costs
confidence 85%Sources used for this update (6)
- www.webstercountycitizen.com — $3.3B 'people mover' rail project delayed - again - at LAX
- lamag.com — 'Blast Incidents' Reported on Troubled LAX People Mover ...
- sjvsun.com — $3.3 billion people mover rail project delayed again at LAX
- www.latimes.com — LAX's long-delayed people mover: The little engine that can't ...
- thedailybs.com — $3.3B ‘people mover’ rail project delayed – again – at LAX
- www.westsidecurrent.com — Fire Damage Delays LAX People Mover Opening to 2027 ...
-
Power rail damage and lawsuits stall LAX SkyTrain
The LAX SkyTrain remains delayed due to damaged guide beams, malfunctioning expansion joints, and power rail damage discovered during September testing. The 2.25-mile automated system is more than $1 billion over its original budget and years behind its initial schedule. A Texas-based contractor has sued LA World Airports, adding legal conflict to the existing technical failures. While passenger service is targeted for early January 2027, the project has become a prominent issue in the mayoral race between incumbent Karen Bass and challenger Nithya Raman.
Why it matters
The $3.3 billion project aims to connect airline terminals to ground transportation. It missed its original 2023 opening date due to certification issues and contractor disputes. The system is now a central transit challenge for the next Los Angeles mayor.
What is confirmed
- The LAX SkyTrain is a 2.25-mile train designed to move passengers from terminals to ground transportation.
- The project is more than $1 billion over its original construction budget.
- The people mover is a campaign issue for mayoral candidates Karen Bass and Nithya Raman.
Still unconfirmed
- September testing revealed damage to the power rail, guide beams, and malfunctioning expansion joints.
- The Texas-based builder has sued LA World Airports.
What to watch next
- Court rulings regarding the contractor lawsuit
- Confirmation of the January 2027 opening date by the consortium
- Results of the Los Angeles mayoral election
confidence 80%Sources used for this update (5)
- laist.com — People Mover delays - LAist
- laist.com — LAX train delays - LAist
- www.latimes.com — L.A.'s next mayor will face transit challenges. Troubled LAX ...
- malibu.fm — Court filings reveal LAX SkyTrain stalled by power rail ...
- article.wn.com — L.A.’s next mayor will face transit challenges. Troubled LAX ...
-
LAX People Mover Faces Fresh Delay Risks
Los Angeles International Airport faces another delay to its automated train system as technical challenges threaten the scheduled debut. Passenger service for the $3.3 billion project is currently targeted for early January 2027, missing its original 2023 opening target. Bondholders granted a two-month reprieve, but the contractor consortium has not committed to the January date. The repeated setbacks stem from ongoing safety testing, certification issues, and contractor disputes. Meanwhile, the project has become a contentious political issue in the Los Angeles mayoral race.
Why it matters
The transit system spans 2.25 miles and aims to connect passengers directly to the airport terminals. Delays have plagued the multibillion-dollar infrastructure effort for years, frustrating travelers and city officials alike. In contrast, regional transit development saw progress elsewhere when Burbank airport opened a new $1.3-billion terminal.
What is confirmed
- The LAX automated train project is valued at $3.3 billion.
- The 2.25-mile SkyLink system was originally scheduled to open in 2023.
- Passenger service is targeted for early January 2027.
Still unconfirmed
- The target for testing, certifying, and preparing the train system is at risk of further slippage.
What to watch next
- Commitment from contractors regarding the January 2027 opening date
- Updates on safety testing and certification progress
- Further bondholder decisions on contractor deadlines
confidence 90%Sources used for this update (2)
- www.latimes.com — Burbank airport's new $1.3-billion terminal opens — bigger ...
- www.dailynews.com — LAX People Mover faces more ‘technical challenges’ ahead of ...
-
LAX People Mover Faces Fresh Delays
The 3.3 billion dollar LAX automated train project is delayed yet again, with passenger service now targeted for early January 2027. Originally scheduled to open in 2023, the 2.25-mile SkyLink system continues to miss deadlines due to ongoing setbacks involving safety testing, certification, and disputes with contractors. Bondholders for the contractor consortium recently granted a two-month reprieve, though contractors have still not committed to the January 2027 opening date. The repeated delays have turned the transit project into a point of contention in the Los Angeles mayor's race.
Why it matters
The protracted timeline for the automated train system exacerbates chronic ground transportation challenges at Los Angeles International Airport. The persistent delays also affect regional infrastructure planning as the city prepares to host large international events.
What is confirmed
- The 3.3 billion dollar LAX automated train project is delayed to early January 2027.
- The system spans 2.25 miles and has faced setbacks involving safety testing, certification, and contractor disputes.
- Bondholders for the contractor consortium building the SkyLink project recently granted a two-month reprieve.
Still unconfirmed
- Contractors will meet the targeted early January 2027 passenger service date.
What to watch next
- Commitment from contractors on the January 2027 opening date
- Resolution of safety testing and certification disputes
- Further updates from project bondholders
confidence 100%Sources used for this update (12)
- spectrumlocalnews.com — What we know about the 2028 LA Olympics so far - Spectrum News
- blog.quikparkbusinessvip.com — LAX People Mover Timeline: 2018 to Still Not Open
- nypost.com — Passengers face travel nightmare as United Airlines cancels flight after brutal 12-hour delay
- nypost.com — lax | Latest News | New York Post
- www.sandiegouniontribune.com — Michael Smolens: Ignoring reality, SANDAG again pushes ...
- londondaily.com — Cathay Pacific to lay off nearly 300 cabin crew in US ...
- www.northcoastcurrent.com — High surf closes coastal rail line through San Clemente
- www.pasadenastarnews.com — Larry Wilson: Trams not moving people at LAX
- travel.yahoo.com — California's LAX Airport Is A Nightmare To Navigate, But Here ...
- blogmickey.com — Rock ‘n’ Roller Coaster Faces Delayed Opening Following Early ...
- www.aol.com — Three years after Israel’s worst catastrophe, one question ...
- www.thedailystar.net — Third Terminal opening delayed to early 2027
-
LAX People Mover pushes passenger service target to January 2027
The 3.3 billion dollar LAX automated train is delayed again, with passenger service now targeted for early January 2027. Contractors have not committed to this new date. The 2.25-mile system faces ongoing setbacks involving safety testing, certification, and disputes with contractors. The project has become a point of contention in the Los Angeles mayor's race as it misses repeated deadlines. Bondholders for the contractor consortium building the SkyLink project recently granted a two-month reprieve.
Why it matters
The train connects terminals, economy parking, the rental car center, and the LAX Metro Transit Center. It was originally scheduled to open in 2023. The project aims to modernize a facility largely built in the 1950s while maintaining active airport operations.
What is confirmed
- The LAX automated train project costs 3.3 billion dollars.
- Passenger service is now targeted for January 2027.
- The automated train covers 2.25 miles.
- The project was originally scheduled to open in 2023.
- Contractors have not committed to the January 2027 launch date.
Still unconfirmed
- The project's delays have taken center stage in the Los Angeles mayor's race.
- Bondholders for the contractor consortium granted a two-month reprieve.
What to watch next
- Confirmation of the January 2027 commitment by contractors.
- Results of final safety testing and certification.
confidence 90%Sources used for this update (15)
- nypost.com — airports | Latest News | New York Post
- www.latimes.com — Will LAX’s troubled and long-delayed people mover train open soon? A new set of delays awaits
- catoday.news — LAX People Mover Delayed to 2027: Travel Update — CA Today
- www.yahoo.com — Delays of LAX People Mover takes center stage in LA ... - Yahoo
- www.newsbeep.com — When will LAX’s troubled and long-delayed people mover train ...
- labusinessjournal.com — SkyLink Lenders Grant Reprieve - Los Angeles Business Journal
- article.wn.com — Troubled LAX people mover delayed again — and it might not be ...
- stmdailynews.com — LAX SkyLink Delayed Again, With Passenger Service Now ...
- ph.headtopics.com — LAX Delays Opening of Automated People Mover Until 2027
- www.golden-state.org — Putting the LAX people mover drama into perspective
- americanvoterpolls.com — LAX People Mover Lawsuit Signals More Delays and Bigger Costs
- foodwadatravel.com — LAX People Mover Delayed Again, New Target Is January 2027
-
LAX People Mover delayed again, now expected in January 2027
The LAX Automated People Mover, a 2.25-mile automated train, has been delayed again and is now expected to open in January 2027. The project, originally scheduled to open in 2023, has faced multiple setbacks. The train will connect terminals, economy parking, the rental car center, and the LAX Metro Transit Center as part of a $3.3 billion project.
Why it matters
The LAX People Mover is a critical infrastructure project aimed at improving transportation within Los Angeles International Airport. The repeated delays have significant implications for travelers and the airport's overall efficiency. The project's challenges have drawn attention from local leaders and are becoming a topic in the LA mayor's race.
What is confirmed
- The LAX Automated People Mover is expected to open in January 2027.
- The project was originally scheduled to open in 2023.
- The People Mover is a 2.25-mile automated train.
- The project cost is $3.3 billion.
- The train will connect terminals, economy parking, the rental car center, and the LAX Metro Transit Center.
Still unconfirmed
- The delays might not be the last, according to some sources.
What to watch next
- The official announcement from LINXS regarding the new opening date
- The impact of the delays on the LA mayor's race
- The final testing and certification process for the People Mover
confidence 85%Sources used for this update (13)
- Los Angeles Times — Troubled LAX people mover delayed again — and it might not be the last time
- LAist — More delays: LAX train contractor buys more time for testing
- KTLA — LAX People Mover opening delayed, again
- CBS News — LAX's long-awaited People Mover project delayed again
- NBC Los Angeles — Opening of LAX Automated People Mover delayed to 2027
- New York Post — LAX’s nightmare ‘people mover’ delayed again three years after scheduled opening
- abc7.com — LAX Automated People Mover train's opening delayed again, this time until at least January 2027, report says
- ABC7 Los Angeles — Delays of LAX People Mover takes center stage in LA mayor's race
- www.latimes.com — Troubled LAX People Mover opening delayed yet again
- nypost.com — Troubled LAX People Mover delayed again - New York Post
- www.cbsnews.com — LAX's long-awaited People Mover project delayed again
- lamag.com — LAX People Mover Delayed Again, Now Expected in 2027
Community Sentiment: How do you assess this situation?
Voice your perspective · Real-time aggregated sentiment from the Live Feeds community